City would give $40 million to developer
The
city will sell bonds to raise $40 million to give to the developer
to build the project. It will cost the city
$80 to $100 million to repay principal and interest. The additional taxes
from the project are used to make the bond payments. If the taxes are
less than the bond payments, the city must make up the difference from
the general fund.
How likely are taxpayers to get stuck with the bill?
Initial projections assumed the building was worth $76 million and
would increase 3.5% per year. Under those assumptions, tax revenues
would be
$96 million. Recent projections assume a value of $82 million increasing
at 2.5%. Those assumptions produce $87 million in revenue.
However, an independent appraisal valued the property at $65.2 million.
The assumption that value will never decline is also problematic. Real
property tax revenues captured by the DDA actually declined between 1992
and 1996 and did not recover until 2002. Projections using the lower
appraised value and assuming a temporary decline in value show tax revenues
$10 to
$20 million short of repaying the bonds.
There are many other things that could go wrong and leave taxpayers holding
the bag. The developer may be unable to rent apartments at projected
monthly rents of $1,050 to $2,200. Interest rates could be higher than
predicted.
Space could take longer to lease than predicted. The construction could
cost more and take longer than expected. A notable real estate failure
was the city subsidized Tally Hall/Liberty Square project, which is currently
empty.
Council goes against advice
Some council members claim that they will not approve the project unless
the financing is secure. However, on August 2, 2004 Council rejected
6-2 a Johnson/Groome amendment that required the city administrator to
certify
tax revenues would be adequate to repay the bond. On June 5, 2006 Council
also voted 8-2 to go forward with the project, even though the city's
chief financial officer said tax revenues were not enough to repay the
bonds.
If the project succeeds, the developer gets the profits. If it fails,
the taxpayers get the bill.
|